The 2026.04.13 SRU Cycle is started

cycle: 13-Apr through 10-May (4 weeks) [1]

08-Apr   Last day for kernel commits and Nvidia graphics drivers.
13-Apr - 17-Apr   Kernel prep week.
20-Apr - 08-May   Bug verification & Regression testing.
Week of 11-May   Release to -updates.

Kernel Versions [2]

questing:
    linux:               6.17.0-24.24
noble:
    linux:               6.8.0-114.114
    linux-hwe-6.17:      6.17.0-24.24~25.10.1
jammy:
    linux:               5.15.0-178.188
    linux-hwe-6.8:       6.8.0-111.111~24.04.1

cycle: 18-May through 15-Jun (4 weeks) [3]

06-May   Last day for kernel commits and Nvidia graphics drivers.
18-May - 22-May   Kernel prep week.
25-May - 12-Jun   Bug verification & Regression testing.
Week of 15-Jun   Release to -updates.

[1] Schedule might change due to an internal Canonical event.
[2] Tentative versions, subjected to change.
[3] Originally preparation started on 11-May but it was shifted due to an internal Canonical event. Note that patch submission deadline is not shifted and it ends on 06-May.

1 Like