Suspended cycle: 17-Nov through 11-Jan (8 weeks)
As the end of the year approaches there would be no way to release a normal 4 week cycle and handle potential issues which might arise. Instead we decided to use the current security cycle which is due to release Dec-01 to address known bugs of high or critical severity along with security fixes.
Normal operation of 4 week SRU cycles will resume 2026.01.12
cycle: 12-Jan through 08-Feb (4 weeks)
07-Jan Last day for kernel commits and Nvidia graphics drivers.
12-Jan - 16-Jan Kernel prep week.
19-Jan - 06-Feb Bug verification & Regression testing.
Week of 09-Feb Release to -updates.