Week Date (Thursday) 26.04 events
October 2025
1 October 16 Toolchain Uploaded
2 October 23
3 October 30
November 2025
4 November 06
5 November 13
6 November 20
7 November 27
December 2025
8 December 04
9 December 11
10 December 18 Ubuntu Testing Week (optional)
11 December 25
January 2026
12 January 01
13 January 08
14 January 15
15 January 22
16 January 29
February 2026
17 February 05
18 February 12
19 February 19 Feature Freeze, Debian Import Freeze
20 February 26 Ubuntu Testing Week (optional)
March 2026
21 March 05
22 March 12 User Interface Freeze
23 March 19 Documentation String Freeze, Kernel Feature Freeze
24 March 23 (Monday) Beta Freeze, Hardware Enablement Freeze
March 26 Beta (mandatory)
April 2026
25 April 02
26 April 09 Kernel Freeze, Non Language Pack Translation Deadline
27 April 16 Final Freeze, Release Candidate, Language Pack Translation Deadline
28 April 23 Final Release

Planned and potentially disruptive archive-wide activities

If you’re planning a change that might have a disruptive effect on the archive - e.g. transitions or switches of important defaults (such as compiler versions) - list it here.

Week Date (Thursday) Planned activity
October 2025
1 October 16 Python 3.14 as a supported version
2 October 23 enable autosync from Debian
3 October 30 Golang 1.25 transition
November 2025
4 November 06
5 November 13
6 November 20
7 November 27
December 2025
8 December 04
9 December 11
10 December 18 binutils 2.46
11 December 25
January 2026
12 January 01 GNOME 50 alpha
13 January 08 Python 3.14 as the default version
14 January 15
15 January 22
16 January 29 GNOME 50 beta
February 2026
17 February 05
18 February 12 GCC 16 as optional
19 February 19
20 February 26
March 2026
21 March 05
22 March 12
23 March 19
24 March 26
April 2026
25 April 02
26 April 09
27 April 16
28 April 23

Ubuntu Resolute Raccoon Release Task Signup Sheet

This signup sheet is to be used for planning release milestone tasks.

The Alpha and Beta 1 milestones have been replaced with Testing Weeks, which are organized ad hoc at this point.

Milestone Date Image (Nusakan) Engineering Checklist Tracking Announcement Email
Feature Freeze n/a n/a @utkarsh
UI Freeze n/a n/a @utkarsh
Doc String Freeze n/a n/a @utkarsh
26.04 Beta
26.04 Release April 23 2026 @utkarsh @utkarsh @utkarsh

When the archive is frozen, all members of the release team are expected to participate in bug fix reviews.

After Feature Freeze, all members of the release team are expected to participate in Feature Freeze Exception reviews in their particular area of expertise.

After Final Beta, all members of the release team are expected to participate in Bug fix reviews in their particular area of expertise.